BTS A/T started:-
Note that the following tests are deleted from the Test schedule.
1. Trans frequency ,
2. Check of feeder cable loss,
3. Check of frequency stability,
4. Check of C/I,
5. Spurious and harmonics.
Vide letter no, TD/NT-GSM-Vol ii -----Dated 14.10.2003.
Check of infrastructure:-
- Earth measurement: - Ask for Earth value record. How much and when
measurement was taken, get the details. Also measure the Earth value
for Exchange as well as tower. Limit :- 0.5
- Antistatic flooring: - Many sites it is observed that antistatic floor is
provided but not connected to earth through 5W/ 1 M resistance. In
some stations copper strip is available but not connected to earth.
- Verify the provision of Fire Detection and alarm system, Fire fighting
equipment, and Emergency light arrangement
- Check Location, Alignment, as per the approved layout plan and Rigidity
of BTS Bay by shaking the Bay.
- Check the status of Power plant and battery if existing, also note down
the peak hour load of the exchange.
- Check the status of existing E/A.
Hardware check of Equipment:-
- As per the specification and purchase order, note and confirm No of Rack,
Rack serial no, no of sectors and thereby no of RTs installed per sectors.
- Note down sector wise Cell ID and ARFCN.
- Write SACFA clearance no as per record.
- Note down no. of TDMA channels, (Eight), LAC, NCC, and BCC.
- Write down all details of Tower and point out the discrepancies.
- Verification of iron work:- As per layout drawing check following items
with respect to cabling and wiring.
Positioning of equipment
Leveling of Rack by spirit level
Quality of RF conectorisation
Crimping of cables
Grounding of feeder cable, Rack, DDF,
Sealing of Feeder cable connection.
- Note down the tilting of Antennas and spacing between the sectors.
- Check the availability of tools, necessary spare modules, and documents
of BTS .
Confirm Q/A report of Power plant, Battery if existing or new. On Lucent BTS there is
no Q/A stamp as it is supplied by vendor
90